Wilmington Health
Site Acquisition
Jacksonville MOB:
- SHG lead on property acquisition and negotiations.
- SHG Handled all due diligence on the site
- 2.46 acres site
Leland MOB:
- SHG lead on property acquisition and negotiations.
- SHG Handled all due diligence on the site
- 2.06 acres
Outpatient Surgery Center:
- Existing site owned by Wilmington Health.
- SHG executed ground lease throughout construction
- SHG handled all due diligence on the site
- 2.74 acre site
Endoscopy Suite Renovations:
- Existing Building interior renovation. No Site work or acquisition required
Project Overview
Jacksonville MOB:
- 20,000 SF
- Single Story Medical office Building
- Family Medicine and Urgent Care practice
- SHG Role:
- Michelle- Lead for programming, space planning, interior finishes and FFE Package
- Managed Architectural, Civil and MEP trades throughout design and construction
- Construction Management
Leland MOB:
- 20,000 SF
- Single Story Building
- Family Medicine Practice
- SHG Role:
- Michelle- Lead for programming, space planning, interior finishes and FFE Package
- Managed Architectural, Civil and MEP trades throughout design and construction
- Construction Management
Outpatient Surgery Center:
- 20,000 SF
- Outpatient Surgery Center
- 4 OR with
- SHG Role:
- Michelle- Lead for programming, space planning, interior finishes and FFE Package
- Managed Architectural, Civil and MEP trades throughout design and construction
- Construction Management
Endoscopy Suite Renovations:
- 13,200 SF Interior Renovations
- Endoscopy Clinic and Outpatient Surgery Center
- SHG Role:
- Michelle- Lead for interior finishes and FFE Package
Design and Construction
Jacksonville MOB:
- $5,500,000 total project Budget
- SHG Managed Design and Construction delivering the project on budget
- Michelle assembled full FFE bid package on the clients behalf
- Total 16 months schedule (including design, permitting and construction)
Leland MOB:
- $6,200,000 total project Budget
- SHG Managed Design and Construction delivering the project on budget
- Total 16 months schedule (including design, permitting and construction)
Outpatient Surgery Center:
- $10,500,000 total project Budget
- SHG Managed Design and Construction delivering the project on budget
- SHG Managed project through multiple lead time challenges working with the contractor on multiple early release packages to ensure an on time delivery of the project.
- Total 15.5 months schedule (including design, permitting and construction)
Endoscopy Suite Renovations:
- Existing Clinic renovation within multi-speciality MOB
- SHG worked with client and architectural team to provide interior design and FFE package.
- Michelle assembled full FFE bid package on the clients behalf
- 13 month schedule (including design, permitting and construction)