Site Acquisition

  • Lead on property negotiations and evaluation
  • Coordinated all due diligence
  • 9.8 acre site
  • Assisted With Negotiating a Development Agreement including Architectural Guidelines with the Town of Clemmons for a Pedestrian Friendly site
  • Preliminary Planning and Development Advisor for Utility Extensions, Use of Outparcels, and Due Diligence of Adjacent Properties

Project Overview

Medical Plaza 1 & 2

  • Two 3-Story 45,000 SF MOB Tower
  • Multi-Speciality Clinics, Spine Center and Rehab
  • SHG managed site, design and construction.

Ambulatory Surgery Center

  • Single Story 12,500 SF outpatient Surgery Center
  • 3 OR’s, 14 Pre/Post Op Bays and varsity of support space
  • SHG managed site, design and construction
  • Site required specialized underground storm water retention with above ground bio cells for water filtration

Design and Construction

Medical Plaza 1 & 2

  • Michelle – Assisted through design and construction, managing interiors and FFE
  • Managed Design Team to ensure program needs were met along with meeting all town architectural requirements.
  • Presented at Town Hall meetings
  • Managed Hard-Stop Budget Established by WFBH Before Design Started – Completed Within Budget

Ambulatory Surgery Center

  • Managed joint venture project between healthcare organizations
  • Managed Completion of Design and All Permitting
  • Managed and controlled a total 19-month schedule (design, permitting, construction)